ATTENTION: A PRE-APPLICATION MEETING IS REQUIRED PRIOR TO SUBMITTAL. WE ENCOURAGE VIRTUAL MEETINGS VIA ZOOM OR TELEPHONE. (Call 208-446-1070 or email to arrange)

Community Development is experiencing a record high volume of land use application submittals. We are committed to providing you with outstanding service, but have limited resources and appreciate your patience while providing the following guideline for sequence and time allotted for processes:Community Planning text with aerial image of neighborhood

  • 3 - 5 days to research after initial request for pre-application meeting received by staff
  • 5 - 7 days for response from Project Planner to schedule time to conduct pre-application meeting
  • 10 - 21 days from initial response contact for pre-application meeting to actually occur

Additionally, Completeness Review may not occur for approximately 5 to 10 days after the application submittal. The application process commences once an application is deemed to be a Complete Submittal and is subject to the Project Planner's schedule.